New delivery times for the delivery of wind turbines to Galway Wind Park have been agreed.
SSE says it has had representations from the local community and politicians regarding the 6am turbine delivery time near Oughterard.
As a result SSE has agreed with Gardaí to change the delivery times from the 5th of January.
Galway Wind Park is a two-phase project which is due to be completed by autumn next year.
It involves windfarms in Cloosh, Lettercraffoe, Seecon and Uggool.
When operational, it’ll have the capacity to generate enough green energy to power more than 80,000 homes.
Turbine deliveries will cross the N59 at the junction with Doon East at the new time of 7a.m for the remaining five months of scheduled turbine deliveries.
Gardaí and the site project team will operate a traffic management plan along the N59 between Roscahill and Moycullen at either side of the junction with Doon Road East from 7am to 7.15am to coincide with turbine deliveries.
↧
Wind turbine deliveries altered after concerns from locals
↧